Project Cost Management
§ important cost
management/calculation terms:
§ sunk cost – cost
already incurred in the past and cannot be recovered, do not consider any more
§ opportunity cost –
difference in value between one path vs alternative (= 100% of the value of next best alternative)
§ value analysis/
engineering – cost reduction without affecting the scope
§ Benefit-Cost
Analysis (BCA) / Cost-Benefit Analysis (CBA) – determine feasibility, bigger
benefit/cost ratio (BCR)
§ Payback Period –
the length of time to recover the investment
§ Return on
Investment (ROI) – the efficiency of investment = (Gain-Cost)/Cost
§ Time Value of Money
– Present Value (PV) = value / (1+interest rate)*year, Future Value (FV) =
value * (1+interest rate)*year
§ Net Present
Value (NPV) = PV of cash inflows – PV of cash outflows (cost)
§ funding for the
project: self-fund, funding with equity, funding with debts
§ discount rate
– rate used to calculate the present value of expected yearly benefits and
costs
Plan Cost
Management
§ Inputs: Project
Charter, Project Management Plan, EEF, OPA
§ Tools &
Techniques: Expert Judgement, Data Analysis, Meetings
§ Outputs: Cost Management
Plan
§ The Cost Management
Plan establishes
§ level of accuracy and level of precision
§ unit of measurement
§ WBS procedure links
(to control account (CA))
§ control threshold
§ earned value rules
of performance, reporting, funding and processes
§ Life cycle costing = total cost
of ownership: production cost, running and maintenance
cost, etc.
§ Data analysis
techniques include:
§ alternatives
analysis — strategic funding options, ways to acquire project resources
Estimate Costs
§ Inputs: Project
Management Plan, Project Documents, EEF, OPA
§ Tools &
Techniques: Expert Judgement, Analogous Estimating, Parametric Estimating, Bottom-up
Estimating, Three-point Estimating, Data Analysis, Project Management
Information System, Decision Making
§ Outputs: Cost Estimates,
Basis of Estimates, Project Document Updates
§ look for ways to
reduce cost
§ ensure the subject
matter experts (SME) to deliver the estimates (which is much more accurate)
§ cost estimate to be
based on WBS
§ Cost Types
§ Variable costs –
costs change with the amount of work, e.g. hourly consultants
§ Fixed costs –
costs that are constant, e.g. equipment leases
§ Direct costs –
directly attributed to the project
§ Indirect costs –
shared costs like AC, lighting, etc.
§ Data Analysis
Techniques
§ Alternatives
analysis
§ Reserve analysis
§ Cost of quality –
cost of conformance and non-conformance
§ Cost Estimate Tools
§ Analogous Estimating
(Top Down Estimate) — compare to a similar project in the past (an estimating
heuristic/rule of thumb)
§ Parametric Estimating — use a
parameter and repetitive units of identical work
§ Bottom-up Estimating —
detailed estimates of each individual activity from historical data, more
accurate and time-consuming
§ Three-point Estimating —
taking into accounts of the pessimistic, optimistic and most likely estimates
§ Activity Cost
Estimates may include indirect cost and contingency reserves
§ usually to be
expressed in a range of values
§ Basis of
Estimates – detailed analysis on how the cost estimate was derived (assumptions,
constraints, possible range (+/-15%), confidence level of final estimate)
Determine Budget
§ Inputs: Project
Management Plan, Project Documents, Business Documents (business case, benefits
management plan), Agreements, EEF, OPA
§ Tools &
Techniques: Expert Judgement, Cost Aggregation, Data Analysis, Historical
Relationships, Funding Limit Reconciliation, Financing
§ Outputs: Cost Baseline,
Project Funding Requirements, Project Document Updates
§ Budget is more about when to spend money
§ Historical
Relationships – analogous/parametric estimation
§ Data Analysis
=> Reserve Analysis – addresses Management Reserve (unknown unknowns) and Contingency Reserve (known risks) [not included in calculation of earned value
management]
§ Funding Limit
Reconciliation – addresses variance between funding limit (e.g. monthly or yearly
limit) and planned expenditure, may require rescheduling of
work to level of the rate of expenditure
§ Value Engineering – to improve
quality/shorten schedule without affecting the scope
§ Project Budget =
Cost baseline (the approved time-phased budget) + Management Reserve
§ when management
reserve is used during project
execution, the amount is added to the cost baseline
§ S-curve: total project
expenditure over project lifecycle
§ Financing: acquiring
funding for projects, may source from internal and/or external sources
Control Costs
§ Inputs: Project
Management Plan, Project Documents, Project Funding Requirements, Work Performance Data, OPA
§ Tools &
Techniques: Expert Judgement, Data Analysis, To-complete Performance Index, Project
Management Information System
§ Outputs: Work Performance
Information, Cost Forecasts, Change Requests, Project Management Plan
Updates, Project Document Updates
§ Check against
the Project Funding Requirements
§ controlling costs
including informing stakeholders of all approved changes and their costs
§ perform Control
Cost more often during execution where money is spent fastest
§ Data analysis
techniques:
§ Earned value
analysis
§ Variance analysis —
including schedule variance (SV), cost variance (CV), schedule performance
index (SPI), and cost performance index (CPI) to check against the
baseline for any variance
§ Trend analysis
§ Reserve analysis
§ Estimate at
Complete:
§ new estimate
required (original flawed)
§ no BAC variance
§ CPI will continue
§ sub-standard
cost/schedule will continue
§ TCPI (To-complete
Performance Index):
§ >1 not enough
funding remain (over budget)
§ <1 more fund
available than needed (under budget)
§ Earned Value
Accrual
§ Discrete Efforts – describes
activities that can be planned/measured for output, including Fixed Formula (activity given a % of budget of
work package at start and earn the remaining
when completed, e.g. 50/50, 20/80 or 0/100), Weighted Milestone (earn
value for milestones of deliverables of the work package), Percentage Complete, Physical Measurement
§ Apportioned Efforts – describes
work that has a direct/supporting relationship to discrete work, e.g. testing,
pm activities, calculated as % of the discrete work
§ Level of Efforts
(LOE) – describes activities without deliverables, e.g. troubleshooting,
assigned the earned value as scheduled, without schedule variance but
may have cost variance
§ SPI at end of
project must be 1
§ SPI is NOT telling
much information about whether the project is on schedule as the Critical Path
must also be investigated to get a meaningful picture
No comments:
Post a Comment