Initiating
|
||||||||||||||
Planning
|
||||||||||||||
Monitoring and
Controlling
|
||||||||||||||
Executing
2. The transition
from one phase to another within a project's lifecycle (e.g., from design to
manufacturing) is typically marked by:
3. Rick has just
been assigned as the project manager of a project to develop a complex product.
The project is in
the Define Scope phase. Which of these tools and techniques will Rick not use
in this phase?
|
5. David was
required to investigate a business problem and describe the higher-level needs
of the business as a whole. David’s final reports describes in detail the
features, functions and characteristics of the product that will meet the
business and stakeholder requirements. What is wrong with David’s report?
David was asked
to analyze the solution requirements but he focused on the business
requirements.
|
David was asked to analyze the business
requirements but he focused on the solution requirements.
|
David was asked
to analyze the functional requirements but he focused on the non-functional
requirements.
|
David was asked
to analyze the non-functional requirements but he focused on the functional
requirements.
|
6. Which of these
tools and techniques is common to all seven Project Integration Management
processes?
Meetings
|
Data analysis
|
Data gathering
|
Expert Judgment
|
|
7. You have a
project in which you are responsible for building a condo complex in a resort
town. The project is expected to take two years to complete. During your work
breakdown structure meeting, you have decomposed many deliverables into work
packages and schedule activities. However, there are some work packages that
will occur a year from now, so you have elected not to decompose those
deliverables and work packages at this time. This is an example of what tool or
technique?
Scope Creep
|
||||
Poor Planning
|
||||
Rolling Wave Planning
|
||||
Time-delayed
Decomposition
|
||||
8. The
organization's safety and health policy, ethics policy, project policy, and
quality policy can be used by a project to influence its success. All these
policies are a part of:
|
9. Which of the
following is an incorrect classification of a feasibility study?
A feasibility
study may be considered a stand-alone project.
|
A feasibility
study may be considered pre-project work.
|
A feasibility
study may be considered the first phase of a project.
|
A feasibility study may be considered a program.
|
10. Which of the
following is the correct logical sequence of the five process groups?
Planning,
Monitoring and Controlling, Initiating, Executing, Closing
|
Planning,
Initiating, Executing, Monitoring and Controlling, Closing
|
Initiating,
Planning, Execution, Monitor and Control, Closing
|
Initiating, Planning, Executing, Monitoring and
Controlling, Closing
|
11. The list of
identified risks is found in the risk register. However, the overall high-level
project risks is first listed in the:
Scope statement
|
||||
Requirement
document
|
||||
Project charter
|
||||
Risk management
plan
|
||||
12. A Work
Breakdown Structure (WBS) dictionary supports the WBS and is a companion
document to the WBS. Which of the following is not included in the WBS
dictionary?
|
13. Close Project
or Phase is the process of completing and concluding all activities across all
process groups to officially close the project. Which of the following
activities is not performed during this process?
Actions required
to transfer completed products to operations
|
Actions required
to archive project information
|
Actions required
to audit project success or failure
|
Actions required to accept the deliverables
|
14. Which of the
following is not a tool and technique of the Collect Requirements process?
Mind mapping
|
Interviews
|
Questionnaires
|
Traceability matrix
|
15. What is a
recommended method for controlling change within a project?
Have only the
project manager able to initiate change.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Have each change approved or rejected through a
formal change control process.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Allow each
project member ultimate control of changes within their realm of the project
without a review process.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Freeze scope and
allow absolutely no changes.
16. Which of
these is an example of a facilitation technique to determine critical
characteristics for new product development?
17. You are
having your project team members record the time they spend on different
activities during the day, such as programming, electrical, HVAC, etc. This
is an example of a tool and technique in what process?
19. Laurence is
the PMO manager at ANZ Company. The CEO of the company asked Laurence to
review the business requirements and develop the current year’s capital
management plan. The capital management plan will outline the key business
deliverables (capital projects) and will go to the board for final approval.
Which of the following organizational artifacts should Laurence review to
analyze the business requirements for the current fiscal year?
21. Although it
is highly recommended that lessons learned are captured and documented
throughout the project lifecycle, lessons learned are finalized during project
closure. At this stage, responses to high-level questions may be gathered and
documented. Which of the following is not an appropriate question to ask at
this stage?
23. Which of the
following is neither an input nor an output of the Direct and Manage Project
Work process?
24. Which of the
following is not an example of a work performance report?
27. Which of the
following processes gives the project management team insights into the
health of the project?
28. Which of the
following is not an input to the Develop Project Charter process?
30. A change
request that is issued to bring the performance of the project back in line
with the project management plan is related to:
|
32. Why are the
approved change requests input to the Direct and Manage Project Work process?
The project team
may reject approved change requests during the Direct and Manage Project Work
process.
|
Approved change requests are implemented by the
project team during the Direct and Manage Project Work process.
|
The project team
monitors approved change requests during the Direct and Manage Project Work
process.
|
The project team
reviews approved change requests during the Direct and Manage Project Work
process.
|
33. The project
manager of a long-term project to develop a new medical device waits until the
later phase where the deliverables are more clearly defined before adding those
details to the WBS. This is an example of:
Poor planning
|
||||||||
Balanced planning
|
||||||||
Deferred planning
|
||||||||
Rolling Wave planning
|
||||||||
34. Which of the
following inaccurately describes a prototype?
|
||||||||
|
36. Projects
operating in agile environments where a high degree of uncertainty exists and
where the scope is not yet fully defined, may not benefit from detailed cost
calculations due to frequent changes. Instead, lightweight estimation methods
can be used to generate a fast, high-level forecast of project labor costs,
which can then be easily adjusted as changes arise. Detailed estimates are:
Reserved for short-term planning horizons in a
just-in-time fashion.
|
|||||
Never developed
in an agile project.
|
|||||
Only developed if
the project stakeholders allow the project manager to do so.
|
|||||
Developed early
during the project but are never updated due to frequent changes.
37. A first-time
project manager was assigned to a project that had a duration of three
months. In order to get a head start on the project,
the manager took
an older, completed the project and incorporated all the tools, techniques,
and checklists in their entirety from
that project into
the current one. The older project was completed in 14 months’ time and was
remarkably similar in nature.
The most
appropriate comment on this would be:
|
No comments:
Post a Comment